Note: An alternative recommendation was brought forward by Councillor Hamilton and seconded by Councillor Earnshaw.
THAT Report 23-190-CD Recreation Complex & Idea Exchange – Concept Design and Budget Approval be received;
AND THAT Council approve design Concept B and direct staff to proceed with schematic design at an estimated total project (design and construction) budget of $107,935,380;
AND FURTHER THAT Council approves increasing the capital forecast for the Recreation Complex A/00463-41 by $24,341,800 for a total construction budget of $101,551,000 funded from tax-funded debt in the amount of $20,610,500, from development charges reserve funds in the amount of $34,352,300, and from development charges funded debt in the amount of $46,588,200.